To estimate the length of time it will take to complete a project, we first break a project down into its components and then estimate the size of each component relative to the others. In estimating the relative size of project components, the principle objective is to identify the smallest component. The development team will then assign project points [ 1 ] to each component based on its size relative to the smallest component.

...